English(EN) The Minnesota Court of Appeals has ruled that the city of Faribault didn’t have enough information about a proposed hyperscale data center when it decided the p

明尼苏达州法院命令对 Faribault 数据中心进行更深入的审查

明尼苏达州法院裁定,Faribault 市在决定拟议的超大规模数据中心项目时,其决定不足。法院认为,该市缺乏足够的信息来确定该项目是否需要更彻底的环境审查。因此,该市必须下令进行环境影响评估,或推迟其决定最多 30 天以收集必要信息。 AI

排序理由 法院就数据中心项目的环境审查做出裁决。[lever_c_demoted from research: ic=1 ai=0.4]