  1. 2026-06-24 regulatory A New Mexico judge dismissed a lawsuit concerning the Project Jupiter data center, but allowed for refiling. source
  2. 2026-06-15 product_launch OpenAI and Oracle are developing a large-scale data center named Project Jupiter in New Mexico. source
SENTIMENT · 30D

5 day(s) with sentiment data

RECENT · PAGE 1/1 · 8 TOTAL
  1. COMMENTARY · CL_112317 ·

    New Mexico report details data center expansion and AI's hidden costs

    A new report details the rapid expansion of data centers in Doña Ana County, New Mexico, examining the challenges and consumer protection issues associated with these facilities. The report, titled "The Hidden Cost of A…

  2. TOOL · CL_109183 ·

    New Mexico judge dismisses Project Jupiter data center lawsuit, allows refiling

    A New Mexico judge has dismissed a lawsuit filed by a Las Cruces resident against the Doña Ana Board of County Commissioners. The lawsuit concerned the board's handling of a vote on the Project Jupiter data center. Whil…

  3. TOOL · CL_98630 ·

    AI data center Project Jupiter recruits influencers in New Mexico

    A marketing agency, Source New Mexico, is enlisting influencers to promote Project Jupiter, an AI data center being built in Doña Ana County. This agency was previously involved in New Mexico's Medicaid re-enrollment so…

  4. SIGNIFICANT · CL_94396 ·

    Oracle's Project Jupiter AI Data Center Sparks Water Usage Concerns in New Mexico

    Oracle's Project Jupiter AI data center in Doña Ana County, New Mexico, is facing scrutiny over its substantial water requirements. Despite Oracle's claims that the water usage is 'negligible' and significantly reduced …

  5. RESEARCH · CL_92446 ·

    OpenAI, Oracle Plan Massive New Mexico Data Center Amid Drought

    OpenAI and Oracle are collaborating on a massive data center project, codenamed Project Jupiter, in Doña Ana County, New Mexico. The facility is planned to span 1,400 acres and require significant electricity and water …

  6. RESEARCH · CL_17306 ·

    North America sees surge in data center development amid AI investment

    North America is seeing significant growth in data center development, driven by hyperscale AI investments. Several states are implementing regulations to manage the infrastructure demands and ensure AI-driven growth do…

  7. RESEARCH · CL_17318 ·

    Oracle taps Bloom Energy fuel cells for massive New Mexico AI data center

    Oracle is redesigning its massive Project Jupiter AI data center campus in New Mexico to use Bloom Energy fuel cells for on-site power generation instead of traditional gas turbines and diesel backup. This shift aims to…

  8. SIGNIFICANT · CL_08038 ·

    Oracle taps Bloom Energy for 2.45GW fuel cell farm to power AI datacenter

    Oracle is significantly expanding its collaboration with Bloom Energy to install 2.45 gigawatts of fuel cell generators at its New Mexico datacenter complex. This move aims to provide substantial power for the facility,…