Only four of the 28 lifts in Queen Mary Hospital's new clinical block will be operational after repairs, with the remaining lifts requiring extensive work until the end of the year. The Architectural Services Department cited frequent operational instability and defects that emerged during final testing, failing to meet contract standards. This issue has delayed the move of clinical services into the HK$13.5 billion block, which began phased opening last November. AI